Câu 48: E20-895: Backup Recovery - Avamar Expert for Implementation Engineers

An EMC Avamar customer has a SQL database that successfully completed a full backup. On the next night, a differential was cancelled due to scheduling concerns. What should be considered for the next backup schedule?

Nội dung câu hỏi

An EMC Avamar customer has a SQL database that successfully completed a full backup. On the next night, a differential was cancelled due to scheduling concerns. What should be considered for the next backup schedule?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Schedule another differential backup at the next backup schedule
  2. B. Schedule a differential backup after running a tail-log backup
  3. C. Schedule a full backup at the next backup schedule — đáp án hiện tại
  4. D. Schedule a full backup after a tail-log backup