Câu 16: E22-285: VxRail Appliance 4.x Deployment and Implementation Exam

You are asked to cable up a VxRail G Series cluster to a redundant pair of 1/10G switches. What is the cabling best practice for this configuration?

Nội dung câu hỏi

You are asked to cable up a VxRail G Series cluster to a redundant pair of 1/10G switches. What is the cabling best practice for this configuration?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cable ports 1 and 2 to one switch. Cable ports 3 and 4 to the other switch.
  2. B. Cable ports 1 and 2 to one switch. Cable ports 3 and 4 to the other switch. Cable BMC from node 1 and 2 to one switch. Cable BMC from node 3 and 4 to the other switch.
  3. C. Cable ports 1 and 3 to one switch. Cable ports 2 and 4 to the other switch.
  4. D. Cable ports 1 and 3 to one switch. Cable ports 2 and 4 to the other switch. Cable BMC from node 1 and 3 to one switch. Cable BMC from node 2 and 4 to the — đáp án hiện tại