CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 2: 312-76: EC-Council Disaster Recovery Professional

Mark is the project manager of the HAR Project. The project is scheduled to last for eighteen months and six months already passed. Management asks Mark that how often the project team is participating in the risk reassessment of this project. What should Mark tell management if he is following the best practices for…

Nội dung câu hỏi

Mark is the project manager of the HAR Project. The project is scheduled to last for eighteen months and six months already passed. Management asks Mark that how often the project team is participating in the risk reassessment of this project. What should Mark tell management if he is following the best practices for risk management?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. At every status meeting of the project team, project risk management is an agenda item. — đáp án hiện tại
  2. B. Project risk management happens at every milestone.
  3. C. Project risk management has been concluded with the project planning.
  4. D. Project risk management is scheduled for every month in the 18-month project.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề