Câu hỏi free preview

Câu 51: 312-76: EC-Council Disaster Recovery Professional

You work as a senior project manager in SoftTech Inc. You are working on a software project using configuration management. Through configuration management, you are decomposing the verification system into identifiable, understandable, manageable, traceable units that are known as Configuration Items (CIs). According…

Nội dung câu hỏi

You work as a senior project manager in SoftTech Inc. You are working on a software project using configuration management. Through configuration management, you are decomposing the verification system into identifiable, understandable, manageable, traceable units that are known as Configuration Items (CIs). According to you, which of the following processes is known as the decomposition process of a verification system into Configuration Items?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Configuration auditing
  2. B. Configuration identification — đáp án hiện tại
  3. C. Configuration status accounting
  4. D. Configuration control