Câu 40: 312-76V3: EC-Council Disaster Recovery Professional
John wanted to transfer his organization's data to an alternate site. He wanted the alternate site to run in parallel to the primary site, which would allow his organization to continue normal business operations almost immediately in the event of a disruption. Which of the following sites is best suited to John's req…
Nội dung câu hỏi
John wanted to transfer his organization's data to an alternate site. He wanted the alternate site to run in parallel to the primary site, which would allow his organization to continue normal business operations almost immediately in the event of a disruption. Which of the following sites is best suited to John's requirements?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Colocation Facilities
- B. Warm Site
- C. Hot Site — đáp án hiện tại
- D. Cold Site
Cộng đồng