Câu 12: ASF: EXIN Agile Scrum Foundation (EX0-008)

During a Sprint Planning session, the team argues about the work estimates for a particular story. ✑ The Product Owner estimates five days. The Lead Architect estimates two days. ✑ The Scrum Master estimates eight days. ✑ The team member working on it estimates seven days. What value (in days) should be used for plann…

Nội dung câu hỏi

During a Sprint Planning session, the team argues about the work estimates for a particular story. ✑ The Product Owner estimates five days. The Lead Architect estimates two days. ✑ The Scrum Master estimates eight days. ✑ The team member working on it estimates seven days. What value (in days) should be used for planning?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. 2
  2. B. 5
  3. C. 7 — đáp án hiện tại
  4. D. 8