A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the third Sprint, the Product Owner says:“I will be going on holiday in 2 weeks. Let’s change the duration of this Sprint to 4 weeks, so that I will be back when it ends.”Should the duration of the sprint be increased?

Nội dung câu hỏi

A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the third Sprint, the Product Owner says:“I will be going on holiday in 2 weeks. Let’s change the duration of this Sprint to 4 weeks, so that I will be back when it ends.”Should the duration of the sprint be increased?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because the Product Owner must be available at the end of a Sprint.
  2. B. Yes, because Sprint duration can be anything between 2 and 4 weeks.
  3. C. No, because the Sprint duration is not based on single events. — đáp án hiện tại
  4. D. No, because only Development Team members may change Sprint duration.