Câu 42: GCPM: GIAC Certified Project Manager

You have recently started a project and assembled the project team which has begun working on the project. However, recently, a project team member has expressed his concerns of having issues with one of the other project team members, and cannot get him to collaborate. What is the MOST appropriate activity for you to…

Nội dung câu hỏi

You have recently started a project and assembled the project team which has begun working on the project. However, recently, a project team member has expressed his concerns of having issues with one of the other project team members, and cannot get him to collaborate. What is the MOST appropriate activity for you to do in this scenario?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reallocate both team members different works so that there is no overlap, by resolving the chance for conflicts.
  2. B. Replace the other project team member immediately with another suitable resource.
  3. C. Meet with both team members, assess the scenario, and be more directive in decision making. — đáp án hiện tại
  4. D. Update your PMO about the conflict and raise a project risk about team disruption.