Câu 27: GCPM: GIAC Certified Project Manager

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project, so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

Nội dung câu hỏi

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project, so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Avoidance
  2. B. Acceptance
  3. C. Mitigation
  4. D. Transference — đáp án hiện tại