Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project, so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?
Nội dung câu hỏi
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project, so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Avoidance
- B. Acceptance
- C. Mitigation
- D. Transference — đáp án hiện tại