Câu 95: GCPM: GIAC Certified Project Manager
Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the fina…
Nội dung câu hỏi
Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Resource leveling heuristics
- B. Critical Path method
- C. Critical Chain method — đáp án hiện tại
- D. Resource utilization
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.