Jane works as a project manager for HRM Inc. Various projects are running under her administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?
Nội dung câu hỏi
Jane works as a project manager for HRM Inc. Various projects are running under her administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Holly's project is behind the schedule.
- B. Holly's project is ahead of the schedule. — đáp án hiện tại
- C. Holly's project is right on target.
- D. Holly's project has costs that are higher than planned.