Câu 46: GCPM: GIAC Certified Project Manager

Rick is the project manager for TTM project. He is in the process of procuring services from vendors. He makes a contract with a vendor in which he precisely specifies the services to be procured, and any changes to the procurement specification will increase the costs to the buyer. Which type of contract is this?

Nội dung câu hỏi

Rick is the project manager for TTM project. He is in the process of procuring services from vendors. He makes a contract with a vendor in which he precisely specifies the services to be procured, and any changes to the procurement specification will increase the costs to the buyer. Which type of contract is this?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Firm Fixed Price — đáp án hiện tại
  2. B. Fixed Price Incentive Fee
  3. C. Fixed Price with Economic Price Adjustment
  4. D. Cost Plus Fixed Fee Contract