Câu 67: GCPM: GIAC Certified Project Manager

You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?

Nội dung câu hỏi

You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Work breakdown structure — đáp án hiện tại
  2. B. Project scope
  3. C. Code of accounts
  4. D. Work breakdown dictionary