CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 4: GCPM: GIAC Certified Project Manager

Which of the following techniques is described in the statement below?"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."

Nội dung câu hỏi

Which of the following techniques is described in the statement below?"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Resource utilization
  2. B. Critical Chain method
  3. C. Resource leveling heuristic — đáp án hiện tại
  4. D. Critical path method

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề