Câu 15: GCPM: GIAC Certified Project Manager

You work as a project manager for HRM Inc. You are working with your team on calculating the project's critical path. You have calculated that one of the activities on the critical path is going to be delayed by six days due to a vendor fault. How will this condition affect the project's completion date?

Nội dung câu hỏi

You work as a project manager for HRM Inc. You are working with your team on calculating the project's critical path. You have calculated that one of the activities on the critical path is going to be delayed by six days due to a vendor fault. How will this condition affect the project's completion date?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The project will be early by six days.
  2. B. The project may be late depending on the amount of float available for the critical path. — đáp án hiện tại
  3. C. The project manager should check to see if float is available for other activities and shift the delayed work to another path.
  4. D. The project will be late by six days.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.