Câu 17: GCPM: GIAC Certified Project Manager
Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind?
Nội dung câu hỏi
Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. To determine the validity of each risk event
- B. To determine the level of probability and impact for each risk event — đáp án hiện tại
- C. To determine the probability and schedule of the risk event
- D. To determine the bias of the risk event based on each person interviewed