Câu 39: GCPM: GIAC Certified Project Manager
You are a new Project Manager that has been entrusted with a software development project. You have started building the list of activities and sequencing them for your project schedule model. As part of the activities, you have identified that your project team will need to start resolving the defects that come out o…
Nội dung câu hỏi
You are a new Project Manager that has been entrusted with a software development project. You have started building the list of activities and sequencing them for your project schedule model. As part of the activities, you have identified that your project team will need to start resolving the defects that come out of the UserTesting, 5 days after the testing starts. Which of the following would be the correct way to represent this logical relationship between the activities?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Start to Start Dependency, with 5 days lead.
- B. Finish to Start Dependency
- C. Start to Start Dependency with 5 days lag. — đáp án hiện tại
- D. Finish to Finish Dependency, with constraint to start after 5 days.