Câu 1: GCPM: GIAC Certified Project Manager

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but…

Nội dung câu hỏi

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project's monitoring and controlling process?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Include the risk response in the project risk management plan.
  2. B. Include the risk responses in the organization's lessons learned database. — đáp án hiện tại
  3. C. Nothing. The risk responses are included in the project's risk register already.
  4. D. Include the responses in the project management plan.