Câu 74: GCPM: GIAC Certified Project Manager
You work as a project manager for HRM Inc. The company has recently opened a new department in its main building. You need information of all the vendors and hardware equipment being used in the different areas of the newly built department. Which of the following charts will you use to get the required information?
Nội dung câu hỏi
You work as a project manager for HRM Inc. The company has recently opened a new department in its main building. You need information of all the vendors and hardware equipment being used in the different areas of the newly built department. Which of the following charts will you use to get the required information?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. OBS
- B. PBS
- C. WBS
- D. RBS — đáp án hiện tại
Cộng đồng