Câu 149: GSLC 2020: GIAC Security Leadership
You are the project manager for the GHY Organization. A stakeholder has presented a change to your project that will cause the project scope to increase considerably. You are considering the change for approval and you need to review the impact of the change on all areas of the project. What change control system comp…
Nội dung câu hỏi
You are the project manager for the GHY Organization. A stakeholder has presented a change to your project that will cause the project scope to increase considerably. You are considering the change for approval and you need to review the impact of the change on all areas of the project. What change control system component is responsible for guiding the review of the impact of all changes on the project management knowledge areas?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Scope change control system
- B. Change control system
- C. Configuration management
- D. Integrated change control — đáp án hiện tại