Câu 46: GSLC 2020: GIAC Security Leadership
Tomas is the project manager of the QWS Project and is worried that the project stakeholders will want to change the project scope frequently. His fear is based on the many open issues in the project and how the resolution of the issues may lead to additional project changes. On what document are Tomas and the stakeho…
Nội dung câu hỏi
Tomas is the project manager of the QWS Project and is worried that the project stakeholders will want to change the project scope frequently. His fear is based on the many open issues in the project and how the resolution of the issues may lead to additional project changes. On what document are Tomas and the stakeholders working in this scenario?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Change management plan — đáp án hiện tại
- B. Communications management plan
- C. Issue log
- D. Risk management plan