An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change ControlBoard in his organization to approve a change to project scope. What should the standardized change management plan require the project manager to do with the approved…
Nội dung câu hỏi
An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change ControlBoard in his organization to approve a change to project scope. What should the standardized change management plan require the project manager to do with the approved scope change?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Perform risk assessment on the new change.
- B. Communicate the change to the vendor.
- C. Create a cost estimate for the change.
- D. Update the WBS. — đáp án hiện tại