Câu 1: HQT-4160: Hitachi Vantara Qualified Professional - VSP 5000 Series Installation

You are installing a VSP 5000 system, it is connected to the power distribution and you now want to power it up. Which three steps should you perform as part of the Power On sequence? (Choose three.)

Nội dung câu hỏi

You are installing a VSP 5000 system, it is connected to the power distribution and you now want to power it up. Which three steps should you perform as part of the Power On sequence? (Choose three.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Turn on the main breakers at the PDUs. — đáp án hiện tại
  2. B. Check that the Power LED on all the CBXs are on.
  3. C. Press the LAN Reset Button on CBX 0.
  4. D. Turn on the PS ON/PS OFF switch on the HSNPANEL0. — đáp án hiện tại
  5. E. Press the Power Button on each CBX. — đáp án hiện tại