Câu 13: HPE7-A12: HPE Network Data Center Professional Architect

Your long-time customer has just acquired a company with 3,500 employees and they are planning on bringing the new data center sites up to their standards. They have asked for a bill of materials given only locations and port counts at the data center sites. What are valid assumptions that should be documented in the…

Nội dung câu hỏi

Your long-time customer has just acquired a company with 3,500 employees and they are planning on bringing the new data center sites up to their standards. They have asked for a bill of materials given only locations and port counts at the data center sites. What are valid assumptions that should be documented in the proposal? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The implementation project manager will be from the acquired company
  2. B. The acquired company's existing contract staff will be hired as full-time employees
  3. C. The IP segments in the existing data centers will remain the same as the acquired company.
  4. D. The acquired company’s physical data cable plant at the new location will meet the technical requirements of the new solution. — đáp án hiện tại
  5. E. The power at the acquired company's data center locations is sufficient for the proposed equipment. — đáp án hiện tại