Câu 47: SPHR: Senior Professional in Human Resources

As an HR Professional you must be familiar with the project management processes and the stakeholders of projects. All projects can map to the project management lifecycle. Which one of the following best describes the project management lifecycle?

Nội dung câu hỏi

As an HR Professional you must be familiar with the project management processes and the stakeholders of projects. All projects can map to the project management lifecycle. Which one of the following best describes the project management lifecycle?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. It is a unique life of each project -from its initiation through its closing.
  2. B. It is the aggregation of the nine knowledge areas of project management: integration management, scope, schedule, costs, quality, human resources, communication, risk, and procurement.
  3. C. It is the life of the management of the project -from initiation, planning, execution, controlling, through closing. — đáp án hiện tại
  4. D. It is the life of a project to interact with all areas including scope, schedule, costs, quality, human resources, communication, risk, and procurement.