Câu 8: H20-688-V1-0: HCSP-Field-SQA V1.0

What is the specified time for performing operations such as service cutover, data setting, removal and insertion of important boards with power on, loading, and power-off reset in the industry?

Nội dung câu hỏi

What is the specified time for performing operations such as service cutover, data setting, removal and insertion of important boards with power on, loading, and power-off reset in the industry?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. 21:00 to 2:00. For the time of performing such major operations on special products, the device specifications shall prevail.
  2. B. 9:00 to 18:00. For the time of performing such major operations on special products, the device specifications shall prevail.
  3. C. Any time
  4. D. Subjected to the customer’s approval time. The recommended time is 00:00 to 6:00. For the time of performing such major operations on special products, the device specifications shall prevail. — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề