Câu 52: C2010-570: IBM Maximo Asset Management V7.5 Implementation
When a Service Level Agreement (SLA) is created, two different types of calendars can be used: an Applies To calendar or a Calculation calendar. Which statement is valid?
Nội dung câu hỏi
When a Service Level Agreement (SLA) is created, two different types of calendars can be used: an Applies To calendar or a Calculation calendar. Which statement is valid?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The Applies To calendar is used when SLAs are applied to other SLAs.
- B. The Applies To calendar specifies the business hours for a particular shift for an organization. — đáp án hiện tại
- C. When both calendar types are left blank, time and shifts are both used as record matching criteria.
- D. The Calculation calendar determines valid values based on a defined SQL query specified by the creator.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.