A tire production company requests to be informed via email if a new custom-tier request approvals take too long. If 20 approval steps take longer than 2 hours, management must be informed. How does a BPM application developer solve this request?The BPM application developer creates:

Nội dung câu hỏi

A tire production company requests to be informed via email if a new custom-tier request approvals take too long. If 20 approval steps take longer than 2 hours, management must be informed. How does a BPM application developer solve this request?The BPM application developer creates:

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. A scheduler which queries the database and sends mail if the condition is met.
  2. B. A SLA with a "Violated N times over period" trigger and "send mail to" as the consequence.
  3. C. A SLA with a "Violated N times over period" trigger and "starts a service" as the consequence. — đáp án hiện tại
  4. D. Tracking points or activates auto tracking and creates a report which shows the required approval-period. The customer can supervise the SLA themselves.