Câu 11: C9550-412: IBM Business Process Management Express or Standard Edition V8.5.5 BPM Application Development
A tire production company requests to be informed via email if a new custom-tier request approvals take too long. If 20 approval steps take longer than 2 hours, management must be informed. How does a BPM application developer solve this request?The BPM application developer creates:
Nội dung câu hỏi
A tire production company requests to be informed via email if a new custom-tier request approvals take too long. If 20 approval steps take longer than 2 hours, management must be informed. How does a BPM application developer solve this request?The BPM application developer creates:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. A scheduler which queries the database and sends mail if the condition is met.
- B. A SLA with a "Violated N times over period" trigger and "send mail to" as the consequence.
- C. A SLA with a "Violated N times over period" trigger and "starts a service" as the consequence. — đáp án hiện tại
- D. Tracking points or activates auto tracking and creates a report which shows the required approval-period. The customer can supervise the SLA themselves.