Câu 13: C9550-412: IBM Business Process Management Express or Standard Edition V8.5.5 BPM Application Development
A BPM application developer is creating a Business Process Definition (BPD) that contains message intermediate events attached to multiple activities. Each of the message intermediate events reference the same undercover agent (UCA). The message must be delivered to the correct process instance and to the correct acti…
Nội dung câu hỏi
A BPM application developer is creating a Business Process Definition (BPD) that contains message intermediate events attached to multiple activities. Each of the message intermediate events reference the same undercover agent (UCA). The message must be delivered to the correct process instance and to the correct activity based on business data. How can the BPM application developer configure the correlation to ensure the message is sent to the correct activity?The BPM application developer must configure the message intermediate event to correlate on the process instance ID and:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. filter on the business data using the activity’s condition tab.
- B. add a script to the BPD that invokes the correct activity based on the business data. — đáp án hiện tại
- C. the business data concatenated into a single variable making it unique for each activity.
- D. the business data by adding a second correlation variable to the UCA and message intermediate event.
Cộng đồng