The primary risk of a wind farm construction project is that it will not be completed timely and on budget. Which of the following describes an impact of this risk?
Nội dung câu hỏi
The primary risk of a wind farm construction project is that it will not be completed timely and on budget. Which of the following describes an impact of this risk?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Cost control tools and monthly reporting do not provide timely updates on the progress of the project.
- B. Project team performance will be assessed as unsatisfactory as no incentives have been provided for the timely completion of the project.
- C. Other construction projects built by the organization were usually late and exceeded their budgets.
- D. Energy not generated by the project will have to be purchased from other sources to fulfill obligations. — đáp án hiện tại