Câu 166: IIA-CIA-PART1: Certified Internal Auditor - Part 1 The Internal Audit Activitys Role in Governance Risk and Control
Which of the following statements is correct with regard to risk management?
Nội dung câu hỏi
Which of the following statements is correct with regard to risk management?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The board's responsibility for risk management cannot be assigned to a board committee, such as a board risk committee.
- B. The chief audit executive is accountable to the board for designing, implementing and monitoring the risk management process.
- C. The total process of risk management, which includes a related system of internal control, is the responsibility of the board. — đáp án hiện tại
- D. The finance director is responsible for the overall implementation of the risk management process.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.