Câu 213: IIA-CIA-PART1: Certified Internal Auditor - Part 1 The Internal Audit Activitys Role in Governance Risk and Control
Which of the following factors related to an organization's performance management system would not contribute to the organization's success?
Nội dung câu hỏi
Which of the following factors related to an organization's performance management system would not contribute to the organization's success?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Performance management is linked to competence and knowledge management.
- B. Subordinates and superiors have shared responsibility for the performance management process.
- C. Staff members own the performance management process, thereby ensuring implementation and accountability. — đáp án hiện tại
- D. Performance management is integrated into other organizational processes and human resource processes.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.