CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 35: IIA-CIA-PART2: Certified Internal Auditor - Part 2 Conducting the Internal Audit Engagement

An audit identified a number of weaknesses in the configuration of a critical client/server system. Although some of the weaknesses were corrected prior to the issuance of the audit report, correction of the rest will require between six and 18 months for completion. Consequently, management has developed a detailed a…

Nội dung câu hỏi

An audit identified a number of weaknesses in the configuration of a critical client/server system. Although some of the weaknesses were corrected prior to the issuance of the audit report, correction of the rest will require between six and 18 months for completion. Consequently, management has developed a detailed action plan, with anticipated completion dates, for addressing the weaknesses. Which of the following is the most appropriate course of action for the chief audit executive to take?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assess the adequacy of the action plan and monitor key dates and deliverables. — đáp án hiện tại
  2. B. Schedule a follow-up audit engagement to assess the status of corrective action.
  3. C. Reassign information systems auditors to assist the information technology department in correcting the weaknesses.
  4. D. Evaluate statistics related to unplanned system outages, unauthorized access attempts, and denials of service to assess the effectiveness of corrections.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề