Câu 127: IIA-CIA-PART2: Certified Internal Auditor - Part 2 Conducting the Internal Audit Engagement
An internal audit manager is supervising an engagement. A senior auditor deviates from the approved engagement plan but meets all deadlines in the approved time schedule. Which activity is not required for the audit manager to provide proper engagement supervision?
Nội dung câu hỏi
An internal audit manager is supervising an engagement. A senior auditor deviates from the approved engagement plan but meets all deadlines in the approved time schedule. Which activity is not required for the audit manager to provide proper engagement supervision?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Actively participate in audit procedures. — đáp án hiện tại
- B. Ensure that all engagement objectives are met.
- C. Approve the deviation from the engagement plan.
- D. Ensure compliance with the time schedule.