A company is in the middle of a large-scale project. Safety concerns have been brought up by several stakeholders, and this has led to numerous proposed changes. The business analyst (BA) must now assess the impact that marking these changes will have on the project. When assessing the impact of safety concerns, which…

Nội dung câu hỏi

A company is in the middle of a large-scale project. Safety concerns have been brought up by several stakeholders, and this has led to numerous proposed changes. The business analyst (BA) must now assess the impact that marking these changes will have on the project. When assessing the impact of safety concerns, which of the following should be considered?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cost/benefit analysis
  2. B. Urgency — đáp án hiện tại
  3. C. Risk register
  4. D. Design