CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 38: CGEIT: Certified in the Governance of Enterprise IT

During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering…

Nội dung câu hỏi

During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering committee's FIRST action?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Require a revised business case.
  2. B. Approve the budget request. — đáp án hiện tại
  3. C. Provide appropriate training.
  4. D. Refer back to the project sponsor for resolution.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề