Câu 38: CGEIT: Certified in the Governance of Enterprise IT
During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering…
Nội dung câu hỏi
During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering committee's FIRST action?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Require a revised business case.
- B. Approve the budget request. — đáp án hiện tại
- C. Provide appropriate training.
- D. Refer back to the project sponsor for resolution.