Câu 484: CISA: Certified Information Systems Auditor

Which of the following is the BEST indication that a software development project is on track to meet its completion deadline?

Nội dung câu hỏi

Which of the following is the BEST indication that a software development project is on track to meet its completion deadline?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Issues identified during user acceptance testing (UAT) have been addressed prior to the original implementation date. — đáp án hiện tại
  2. B. Technical specifications and development requirements have been agreed upon and formally recorded.
  3. C. Project plan due dates have been documented for each phase of the software development life cycle.
  4. D. The planned software go-live date has been communicated in advance to end users and stakeholders.