Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?
Nội dung câu hỏi
Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Information gathering techniques
- B. Data gathering and representation techniques
- C. Planning meetings and analysis — đáp án hiện tại
- D. Variance and trend analysis