You are the project manager of GHT project. Your project utilizes a machine for production of goods. This machine has the specification that if its temperature would rise above 450 degree Fahrenheit then it may result in burning of windings. So, there is an alarm which blows when machine's temperature reaches 430 degr…
Nội dung câu hỏi
You are the project manager of GHT project. Your project utilizes a machine for production of goods. This machine has the specification that if its temperature would rise above 450 degree Fahrenheit then it may result in burning of windings. So, there is an alarm which blows when machine's temperature reaches 430 degree Fahrenheit and the machine is shut off for 1 hour. What role does alarm contribute here?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Of risk indicator — đáp án hiện tại
- B. Of risk identification
- C. Of risk trigger
- D. Of risk response