Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implem…
Nội dung câu hỏi
Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Transference — đáp án hiện tại
- B. Mitigation
- C. Acceptance
- D. Avoidance