Câu 1: Isaca Certified in Risk and Information Systems Control
David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000.…
Nội dung câu hỏi
David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Avoidance — đáp án hiện tại
- B. Mitigation
- C. Acceptance
- D. Transfer
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.