Câu 434: Isaca Certified in Risk and Information Systems Control
You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?
Nội dung câu hỏi
You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Negative risk response, because crashing will add risks.
- B. Positive risk response, as crashing is an example of enhancing.
- C. Positive risk response, as crashing is an example of exploiting. — đáp án hiện tại
- D. Negative risk response, because crashing will add costs.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.