Câu 228: Isaca Certified in Risk and Information Systems Control
You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk management, and risk categories. You discover that the risk categories have not been created. When the risk categories should have been created?
Nội dung câu hỏi
You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk management, and risk categories. You discover that the risk categories have not been created. When the risk categories should have been created?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Define scope process
- B. Risk identification process
- C. Plan risk management process — đáp án hiện tại
- D. Create work breakdown structure process
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.