Câu 18: CAP: Certified Authorization Professional

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager…

Nội dung câu hỏi

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Project costs will increase. — đáp án hiện tại
  2. B. The amount of hours a resource can be used will diminish.
  3. C. The project will take longer to complete, but risks will diminish.
  4. D. Project risks will increase.