Câu 15: CAP: Certified Authorization Professional

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?

Nội dung câu hỏi

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Risk-related contract decisions
  2. B. Project document updates
  3. C. Risk register updates
  4. D. Organizational process assets updates — đáp án hiện tại