CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 113: CAP: Certified Authorization Professional

You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to th…

Nội dung câu hỏi

You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cost management plan
  2. B. Procurement management plan — đáp án hiện tại
  3. C. Stakeholder register
  4. D. Quality management plan