Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?
Nội dung câu hỏi
Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. New or omitted work as part of a risk response can cause changes to the cost and/or schedule baseline. — đáp án hiện tại
- B. Risk responses protect the time and investment of the project.
- C. Baselines should not be updated, but refined through versions.
- D. Risk responses may take time and money to implement.