Câu 104: CAP: Certified Authorization Professional
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniqu…
Nội dung câu hỏi
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Risk acceptance
- B. Risk avoidance
- C. Risk transference — đáp án hiện tại
- D. Risk mitigation
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.