Requirements elicitation: Your company has received a customer contract to develop a system for the scheduling of the customer’s delivery vans. It is your task to identify the requirements for this scheduling system. You have arranged appointments for interviews with three key members of the customer’s staff, and are…
Nội dung câu hỏi
Requirements elicitation: Your company has received a customer contract to develop a system for the scheduling of the customer’s delivery vans. It is your task to identify the requirements for this scheduling system. You have arranged appointments for interviews with three key members of the customer’s staff, and are now preparing interview questions. Which of the questions below are appropriate interview questions for the requirements elicitation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. What are the most important technical terms for the application and how are they defined?
- B. If the delivery deadline is not met, is a contract penalty to be paid?
- C. What data quantities / data rates are to be processed? — đáp án hiện tại
- D. When is the installation of the completed system to be started?