Câu 12: ATA: Advanced Test Analyst

Which of the following criteria on test progress would enable the business to determine a likely go live date?(i) Number of tests planned versus number of tests executed(ii) Number of high priority defects outstanding(iii) The test teams timesheets in order to show how much effort has been devoted to testing(iv) Numbe…

Nội dung câu hỏi

Which of the following criteria on test progress would enable the business to determine a likely go live date?(i) Number of tests planned versus number of tests executed(ii) Number of high priority defects outstanding(iii) The test teams timesheets in order to show how much effort has been devoted to testing(iv) Number of tests passed and number failed(v) Number of defects found in each development area(vi) The rate at which defects are being found

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. (ii), (iii), (iv)
  2. B. (i), (iii), (v)
  3. C. (i), (ii), (vi) — đáp án hiện tại
  4. D. (iv), (v), (vi)